Single crown
A single crown of designed capacity is installed over the test pile. Suited to standard working-load proof tests and to crowded sites where a conventional kentledge platform cannot be accessed.
A pile load test measures what a pile will actually carry, rather than what the calculation says it should. Apex carries out static compression testing with crown and reaction-beam systems, dial-gauge instrumentation and a full written report.
Static pile load testing — quick facts
| Service | Static compression pile load testing |
|---|---|
| Purpose | Directly measure a pile's capacity and settlement under applied load |
| Reaction systems | Single crown, stacked successive crowns for high loads, reaction beams for uplift and compression |
| Jacking | Hydraulic jacks 500–5000 tonne, 700 bar working pressure |
| Instrumentation | Dial gauges 10, 30 and 50 mm range, 0.01 mm graduation |
| Load measurement | Load cell 0–10 000 kN with digital indicator, 1 kN resolution |
| Deliverable | Load–settlement record and written test report |
What it is
A pile load test in the UAE is a direct measurement of a pile’s geotechnical capacity. Load is applied in controlled increments through a hydraulic jack reacting against kentledge or a reaction beam, and settlement is recorded at each stage on dial gauges mounted to an independent reference frame.
The output is a load–settlement curve: how much the pile moved, at what load, and how much of that movement came back on unloading. That curve confirms whether the as-built pile meets the design assumption, or shows where the design needs revising before the rest of the piles are installed.
Apex has procured jacking and measuring equipment specifically for this work, and in-house designs are developed for each project from the loads and access supplied. Data records are generated and preserved for cross-checking.

Reaction systems
The system is chosen from the magnitude of the load, the capacity of the pile and how much room there is around it.
A single crown of designed capacity is installed over the test pile. Suited to standard working-load proof tests and to crowded sites where a conventional kentledge platform cannot be accessed.
Successive crowns installed one over the other for mega load tests, where the required reaction exceeds what a single crown can provide.
Beams spanning between anchor piles, used where uplift as well as compression must be tested, or where kentledge cannot be delivered to the working area.
Sequence
Test pile, working load, maximum test load, loading increments and hold times are confirmed with the geotechnical engineer against the project specification.
A kentledge crown is assembled over the pile, or reaction beams are set against anchor or reaction piles. For very high loads, successive crowns are stacked one over the other.
Dial gauges are mounted on an independent reference frame clear of the reaction system so that settlement readings are not affected by movement of the kentledge.
Load is applied in stages through the hydraulic jack and held at each increment, with settlement recorded at set intervals until the rate of movement stabilises.
The pile is unloaded in stages and elastic rebound recorded, which separates recoverable settlement from permanent displacement.
Readings are worked up into a load–settlement curve and a written report, with all raw data records preserved for cross-checking.
Equipment
Pile load testing equipment
| Item | Specification |
|---|---|
| Hydraulic jacks | 500 to 5000 tonne capacity, 150 mm stroke, 700 bar |
| Electric power packs | 7.5 HP / 5.5 kW, two-stage 100–700 bar |
| Load cells | Type PRE, 0–10 000 kN, 1% full-scale precision |
| Digital indicator | Indipoc µP1, ranges 600–3000 kN, 1 kN resolution |
| Dial gauges | 10 mm / 30 mm / 50 mm range, 0.01 mm graduation |
| Reaction crowns | Single and successively stacked for mega load tests |
| Reaction beams | For uplift and compression testing |
Dial gauge accuracy
| Measuring range | Graduation | Accuracy | Hysteresis |
|---|---|---|---|
| 10 mm | 0.01 mm | ±13 µm | 5 µm |
| 30 mm | 0.01 mm | ±25 µm | 7 µm |
| 50 mm | 0.01 mm | ±35 µm | 9 µm |
Project references
Questions
A pile load test applies a known load to a pile and measures how far it settles, which is the most direct way to establish a pile's capacity. Unlike a calculation from soil parameters, it measures the pile as actually built in the ground on that site.
Testing is normally specified where ground conditions vary across the site, where strata are weak or unpredictable, or where the authority or structural engineer requires verification of the design assumptions. Bored piles in variable ground are common candidates, because there is no reliable driving record to infer capacity from.
A static load test applies real load to the pile and measures settlement directly, so it is the more precise method for determining capacity. Dynamic pile analysis (PDA) infers capacity from the response to an impact and is faster and cheaper. The most reliable programmes use static tests on a small number of piles to calibrate the PDA results on the rest.
Test load is set by the specification, and is typically a multiple of the design working load — commonly 1.5 times working load for a proof test and higher for an ultimate or preliminary test. The reaction system is sized to the maximum test load, which is why very high loads need stacked crowns rather than a single kentledge.
Setting up the reaction system and instrumentation is usually the longest part. The loading cycle itself depends on the number of increments and the hold time at each, which the specification sets. Maintained-load tests with long holds at working load take considerably longer than a quick proof test.
Yes. Crown-based reaction systems suit crowded or congested areas where a conventional kentledge platform cannot be accessed, and the system is selected from the magnitude of the load and the capacity of the pile to be tested.
Enquiry
Send the pile schedule, working load, required test load and site access details and we will come back with a method and a price.
Reach us directly
Call, WhatsApp or email — all three reach the same team, and we reply within one working day.
Call +971 4 320 4120WhatsApp +971 55 221 9418Email apex@eim.aeSite owner: set NEXT_PUBLIC_FORM_KEY to enable the enquiry form.
Next step
Excavation dimensions, formation level and a soil report are enough to price most dewatering jobs. We reply within one working day.